Delivery status

MVP delivered. Phase 1 in progress.

A day-by-day view of where the CHIRPdb build stands against its allocated budget. Phases map to the delivery packages on the roadmap.

Last updated 31 Jul 2026
Complete
MVP
19.5days
Foundation delivered
In progress
Phase 1 · Foundation
Not started
Remaining · P2 + P3 + P5
48days
After Phase 1 wraps
Post-MVP timeline

Where we are in the 83-day plan

MVP 19.5d
Phase 1 35d
Phase 2 23d
P3 10d
Phase 5 15d
Delivered
In progress
Not started
Phase breakdown
MVP Foundation MVP Complete
19.5 / 19.5 days
Phase 1 P1 · Foundation In progress
Phase 2 P2 · Verification & provenance Not started
0 / 23 days
Phase 3 P3 · Semantic layer Not started
0 / 10 days
Phase 5 P5 · Production hardening Not started
0 / 15 days
Overall (post-MVP)

Progress across the 83-day budget

0%
Day 0 Day 83